Units Lagging in Coal Production as on : 11-02-2026
 

Mines Lagging

CompanyStateConstituencyUnit NameOnDate Target ('000 Te)OnDate Actual ('000 Te)
BCCLJHARKHANDDHANBADPB PROJECT COLLY COAL MINE UG.59.06
BCCLJHARKHANDGIRIDIHMADHUBAND UG.840
BCCLJHARKHANDGIRIDIHJOGIDIH MINE OC.430
BCCLJHARKHANDGIRIDIHMAHESHPUR MINE OC.43.4
BCCLJHARKHANDDHANBADRAJAPUR/SJ-HIGHWALL UG MINING2.680
BCCLJHARKHANDGIRIDIHHW MINING PROJECT(ABOCP)1.741.33
BCCLJHARKHANDGIRIDIHMURAIDIH UG1.790
BCCLJHARKHANDGIRIDIHMUDIDIH COLLIERY3.271.76
BCCLJHARKHANDDHANBADAMLG. JOYRAMPUR COLLIERY OCM2.68.81
BCCLJHARKHANDDHANBADKENDUADIH MINE OCM.610
BCCLJHARKHANDGIRIDIHASGKCC OC.89.32
BCCLJHARKHANDGIRIDIHDAMODA MINE OCM1.191.1
BCCLJHARKHANDDHANBADMOONIDIH COLLIERY UG1.871.7
BCCLWEST BENGALASANSOLDAMAGORIA COLLIERY OCM1.720
BCCLWEST BENGALDHANBADBASANTIMATA-DAHIBARI OCM2.382.16
BCCLJHARKHANDDHANBADAMLG. N.T.S.T. JEENAGORA OCM2.380
BCCLJHARKHANDDHANBADKUYA OCM5.96.6
BCCLJHARKHANDDHANBADBASTACOLLA OCM6.716.2
BCCLJHARKHANDDHANBADGONDUDIH KHAS KUSUNDA OCM4.394.28
BCCLJHARKHANDGIRIDIHEAST BASSURIYA COLLIERY OCM1.510
BCCLJHARKHANDDHANBADNEW GODHUR KUSUNDA ALKUSHA OCM5.931.4
BCCLJHARKHANDDHANBADAMLG. DHANSAR INDUSTRY OCM2.92.14
BCCLJHARKHANDGIRIDIHBANSDEOPUR OCM.21.2
BCCLJHARKHANDGIRIDIHTETULMARI OCM1.860
BCCLJHARKHANDGIRIDIHSENDRA BANSJORA COLIERY OCM3.86.66
BCCLJHARKHANDGIRIDIHAMLG KESHALPUR WESTMUDIDIH OCM10.44.18
BCCLJHARKHANDGIRIDIHASGKCC UG.180
BCCLJHARKHANDGIRIDIHNEW AKASHKINAREE COLLIERY UG.1.06
BCCLJHARKHANDGIRIDIHKHARKHAREE MINE UG.520
BCCLJHARKHANDGIRIDIHJOGIDIH MINE UG.060
BCCLJHARKHANDGIRIDIHAMLG. BLOCK II OCM14.7113.72
BCCLJHARKHANDGIRIDIHAMLG. MURAIDIH PHULARITAND OCM16.2811.74